A snagging checklist for a new building or flat handover

A snagging checklist for owners and managers taking over new flats or a new tower from a developer: what to test, how to photograph it, how to track fixes.

Snagging is a structured walk of a new flat or building before or soon after handover, testing everything that can be tested and photographing every defect, so the developer fixes it while it is still their responsibility. Do it room by room with a fixed list, give every snag a number, a photo and a location, and track each one until the developer's fix is checked, not just reported.

Why snags become your costs

Developers usually fix defects reported within the defects period set in the sale or handover documents. After that, the same leaking joint is a repair on the owner's bill. The defects that cost most later (hidden leaks, poor drainage falls, AC drain lines with no slope) are exactly the ones a quick walk misses. The length of the defects period and what it covers depend on your contract and local rules; check them.

Before the walk

  • Ask for the handover pack: drawings, equipment list, warranties, test certificates.
  • Bring: phone with space for many photos, torch, spirit level or level app, socket tester, a bucket and a towel, masking tape to mark snags.
  • Have the water, power and AC on. A snag walk with no utilities misses half the faults.

The checklist

Mark each item OK or Snag, with a photo and a short note.

AreaTest
DoorsOpen and close fully, no rubbing, locks and handles work, gaps even
Windows and balcony doorsOpen, close, lock; seals intact; no light or draught at the frame
Walls and ceilingsCracks, uneven paint, stains (look for water marks)
FloorsHollow tiles (tap them), cracked tiles, uneven grout, skirting gaps
KitchenCabinets aligned, drawers run, worktop sealed, sink drains fast, no leak under it
BathroomsTaps hot and cold, shower pressure, water drains to the floor drain (pour a bucket), silicone complete, toilet flushes and refills, extractor fan runs
Water heaterHeats, no leak, safety valve fitted
ACEach unit cools, no drip after 20 minutes, drain line slopes and empties, remote works
ElectricalEvery socket tested, every light and switch works, panel labelled
BalconyFloor drains to the outlet (pour water), railing firm
Smoke and fire devicesPresent where shown on the drawings
FixturesWardrobes, mirrors, towel rails firm
MetersReadings photographed, numbers match the documents

For a whole building, add plant rooms, pumps, tanks, lifts, car park drainage, roof and common areas, and list each piece of equipment with its warranty date; the facilities handover checklist covers the documents and keys. Once residents move in, the move-in inspection checklist takes over.

How to record a snag

Each snag needs:

  1. A number (402-017).
  2. The exact place (402, master bathroom, shower floor near drain).
  3. A photo with something for scale, and the masking tape mark visible.
  4. What is wrong in one line.
  5. Status: reported, fixed by developer, checked.

Never close a snag on the developer's word. Check it, photograph it, then close it.

After handover: keep the snags and the history together

Most snag lists live in a spreadsheet sent back and forth by e-mail until nobody knows which version is current. Once you take over, the snags and every later repair belong to the same units and machines.

In UnitVO, each snag can be reported from the unit's QR sticker with its photo and becomes a job for that unit, which can only be finished with an after-photo; the technician works from the technician app in the phone's browser. Equipment from the handover pack goes into the equipment register with model, location and warranty end date, with a QR code on each machine, so the warranty clock is visible from the first repair (equipment warranty tracking explains the habit). Each unit gets its own QR sticker, so the first residents can report faults from day one. See QR codes.

UnitVO does not send snags to the developer or manage the developer's work; it keeps your record of what was found and what was fixed. If your list lives in a sheet today, UnitVO vs spreadsheets shows where to start.

When this is not for you

For a single flat, a printed checklist and your phone are enough, or a professional snagging inspector if you prefer an expert report. For a whole building, the developer's handover procedure and your contract decide who inspects and how; use this list to prepare, not to replace that procedure. Read who UnitVO is not for.

What it costs

Every plan has every feature. In the International region: Free (5 units, USD 0), Pro USD 49, Team USD 75 and Portfolio USD 199 a month, billed yearly. Each region has its own price list in its own currency; prices are before tax, and UAE customers pay 5 % VAT at checkout. The 30-day trial has Team features for up to 50 units and needs no card. See pricing.

Questions and answers

What is snagging?

A detailed inspection of a new flat or building to find defects, so the developer fixes them during the defects period.

When should snagging be done?

Before or as soon as possible after handover, with the water, power and AC switched on.

How long does the developer have to fix snags?

That depends on your sale or handover contract and local rules. Check both and report snags in writing within the period.

How do I prove a snag was fixed?

Check it yourself, take an after photo from the same angle, and only then mark it closed.